Before approving monthly construction payment certificates or submitting draw requests to project owners, verify your schedule of values conforms to these mandatory mathematical rules.
Column G Total Completed & Stored Equality Check
In every line item on the AIA G703 Continuation Sheet, the total completed and stored value must strictly equal the sum of previous work (Column D), current period work (Column E), and stored materials (Column F).
Balance to Finish (Column I) Reconciliation
Column I represents the remaining contract balance to be billed. It must exactly equal the Scheduled Value (Column C) minus Total Completed and Stored (Column G).
G702 Line 4 Cross-Document Agreement with G703
Line 4 on the G702 summary certificate (*Total Completed and Stored to Date*) must equal the exact grand total sum of Column G on the continuation sheet. Even a 50¢ discrepancy triggers an immediate architect rejection.