Top 5 Reasons Construction Pay Applications
Get Rejected by Architects & GCs
A single mathematical discrepancy or unapproved change order on your AIA G702 / G703 can reset your 30-day payment clock. Here is how to prevent rejections.
1. G703 Column G Does Not Equal Previous + This Period + Stored
The most common human error in Excel. When accountants manually copy formulas or paste static values, Column G drifts from Column D + E + F. Project managers will reject the draw request on the spot.
2. Discrepancy Between G702 Line 4 and G703 Column G Total
Line 4 on the summary certificate (Total Completed & Stored to Date) must precisely match the bottom-line grand total of Column G on your continuation sheet. Even a 10¢ rounding variance triggers rejection.
3. Line Items Billed Beyond 100% (Overbilling Without Change Order)
If Column G exceeds Column C (Scheduled Value), Column I (Balance to Finish) becomes negative. Owners and architects are legally prohibited from certifying payments for work not backed by an executed change order.
4. Inaccurate Retainage Calculation on Stored Materials
Contracts often dictate different retainage percentages for work completed (e.g. 10%) vs. materials stored off-site (e.g. 0% or 5%). Calculating standard retainage across the entire lump sum violates contract terms.
5. Unapproved or Pending Change Orders Billed on Line 2
Contractors often bill for verbal change directives before the prime contract modification is counter-signed. General contractor accounting software (e.g. Procore, Textura) will reject the draw request.